~Setitis Tinta~

My photo
Metropolis Serendah, Selangor, Malaysia
Readers today, Leaders tomorrow

5/22/2010

7th week of internship



This week, I had assisted Ahmad Shahir (field engineer) to complete the procedure for concrete collar installation. I helped him to do the engineering drawing using the engineering software (AUTOCAD 2007). I had learned a lot to familiarize with the software even though I had learned the basic of AUTOCAD during my study in UNITEN.

Below are some of my job done;



This is the concrete collar operation approach that will be implemented in OMBAK project.
The left hand side is the diagram of the barge. The position is as in the drawing. The right hand side is the vessel functioned same as the barge but in the shallow water area.




As above picture, the top one is the installation that will be done by the vessel in the shallow area. The concrete collar will be lifted by the crane from the vessel towards the desired position on the pipeline. The bottom of it is the installation done by the barge. The procedure is the same as the vessel but work done in the water depth more than 1 meter.




This is water jetting method. This method will be implemented towards the buried pipeline to expose the pipeline for the concrete collar installation. The water jet will blow high pressure water to the seabed to expose the pipeline and remove the soils.



Above is the method to measure the spacing of the concrete collar using the 1.5 metres steel bar. the spacing need to achieve 3 meters space between the concrete collar so, the diver need to dummy the steel bar twice on the pipeline to obtain the required space length. Finally, the point will be mark by the floating buoy for the reference point to lower down the concrete collar towards the crews on the vessel.






This is the method to use to lift the concrete collar. The crane hook will be attached by the soft-eye both end sling that had been tied to the shackle. Shackle will be clamp towards the pfeifer quicklift on the concrete collar before lifting.

5/18/2010

6th week of Internship

ANCHOR HANDLING PROCEDURE

Anchor handling is the activities pertaining to mooring, relocating, adjusting, retrieving anchors on barges and workboats.

To handle an anchor, barge should be moored to the exact location with high concerned on the safety issue because the operation is potentially dangerous. To achieve this purpose, the whole move of the barge must methodically plan and prepared to obtain maximum efficiency and safety.

In the planning, things to be considered are the location of the work site, the water depth (whether the barge could attain that depth), type of bottom on location (normally soil), weather condition and approach course.

The anchoring process shall use the suitable type of anchor with enough holding power in the soil condition at the site. This selection will be considered based on the size of the barge.

Anchor pennant buoys are required for deployment and retrieval of anchors to identify the location of the anchor at the seabed. The buoy is painted with visible colour example day glow or international orange.

Anchor winches is the machine that provide the tension on the anchor wire during anchor deployment or relocation and as a machine to retrieve the anchors by reel-in the anchor wire. Anchor wire shall have adequate tension force to hold the anchors.

During the anchor handling process, communication is very crucial to avoid faultiness. Device such as walkie-talkie is commonly used by the crews.


SETTING AND ANCHORING OF ANCHOR


To choose the anchor, holding power is the main thing to be considered. Below is some calculation to determine the holding power:

FLUKE AREA (m²) x PENETRATION (m) = TONS (m³)

Then, the fluke or shank angle should be appropriate with the type of the seabed. Different soil needs different angle of fluke/shank. The principle will be explained below:

1. In hard soil, an anchor with a fluke angle of 32 degrees will give the highest holding power.

2. In hard soil, 50 degree fluke shank angle will obstruct penetration and the anchor will begin to trip, fall aside and slide along the seabed.

3. In mud, 32 degree fluke shank angle will not penetrate sufficiently.


STEVTENSIONER


Stevtensioner is used for tensioning anchor cables. This is the case when insufficient powerful equipment was installed or the installation of powerful equipment was too expensive.

The full anchor system will be tensioned before linking up and fully ready for the arrival of the floating object, vessel or buoy at the anchor location. Then, it is secured by immediate link-up.


The dead end of the passive chain is connected to the tensioner. The work chain, B is led through the tensioner.

PRINCIPLE:

· When pulling vertical direction on the work chain, tensioner will be lift up. The chain will experience the stretching.

· When no more stretching is possible, tensioner will be moved upward by the vertical force.

· The tensioner does not allow the chain to slide back, so the horizontal chains will drag the anchors into the soil. Consequently the holding power of the anchors increases.


MULTI TENSIONER



Multi tensioner will tension multiple anchor lines in the installation phase and offers permanent fixation of a web of anchor lines near the sea floor. Anchors, multi tensioner and sub-sea buoy have have been combined in a new cost effective alternative mooring. The advantages of the system are most evident in moorings in deep water. New applications have been described for the mooring of production and tension leg platforms with special attention paid to simple installation methods without the use of divers.

PRINCIPLE:

(Based on the development of the stevtensioner)

Multi-tensioner handles multiple lines and consists of one chain locking device per anchor line situated for instance on a ring (figure) or mounted like a Christmas tree around a vertical pipe member. The chain locking devices can also be attached to the base of a floating tower or ballast frame for a tension leg platform. To allow motion in the vertical plane they can be fixed on hinges.

MOORING LINES

Mooring systems are designed with sufficient strength to maintain a unit on location under all circumstances. The design calculations must accommodate conditions met in worst weather.

Commonly, most rigs were equipped with chains as mooring lines. In deep water, the mooring lines were replaced by composite mooring system because;

· The weight of the chain made handling impossible

· Once the mooring line was installed there was a very steep chain angle near the fairlead due to the chain’s weight. This rendered the movement of the rig unacceptable due to the wind and waves.


To solve this problem, a composite mooring system will be used.

Some suggestions which influence the catenary and consequently the forces in the mooring system are given below;

1) The buoy can be connected to the anchor line by means of a special permanent chain lock-chaser.



2) When using relatively long mooring lines in shallow waters, the effect of the rig movement on the systems can be optimized by applying a ballast weight within the system.




3) To optimize the chain or rig angle a combination of buoy and ballast permits a closer rig mooring.



BREAKING OUT FORCES

Breaking out forces is related to the holding power applied. If an anchor has not penetrated too deeply (thus giving a low holding efficiency) it can easily be broken out. Consequently, some users apply oversized anchors. However if an anchor has penetrated deeply and has been subjected to a high load, it will then be proportionally more difficult to break out.

Second factor influencing the forces required for breaking out is the design of the anchor.

The types of soil clearly influence breaking out forces, regardless of the anchor type.

· In sandy soils, the breaking out force is approximately 12-17% of the load held.

· In clay it is 60%

· In soft soils it will be even higher

· In sticky soils it can exceed 100%

(These approximations are applicable to any anchor type.)


5/06/2010

5th Week of Internship

In oil and gas, pipeline is not laid alone on the ground or seabed. Sometimes, it will be clamped with the other pipe or cable along the pipeline. Pipeline clamp exist in various types. Some of them are piggy back clamps, riser clamps and umbilical clamp.





Piggyback clamping system uses a moulded saddle, tailored to the radius of the main line and is secured by circumferential straps. The saddle, which encompasses the secondary line holding it in place, has an axial split on its base to allow easy installation of the secondary line.



Clamps can be manufactured from various materials, including rubber, polypropylene and polyurethane elastomer and etc.







Metallic straps are offered in carbon steel, stainless steel or inconel depending on the specified design life of the system with Kevlar straps also as an option.



The other type of clamp is bundle clamp. It is for small bore service and injection lines that are secured at regular intervals to provide an effective solution to laying subsea lines simultaneously.









These lines will remain on the seabed. Certain cases, pipeline will be buried under the seabed to avoid the external forces that may cause harm to the pipeline. For example, fishing activity, anchor drop and drag from the vessel and etc.