9th week of the internship

This week, I had assisted Khairul Azmi to complete the proposed Master Document register for Sabah Oil and Gas Terminal. This document contains the tasks to be done in certain project. The tasks are divided into several parts. Engineering procedures, operation procedures, welding procedures, QAQC procedures, marine procedure and as built report are the parts in the Master Document.

I also had been assigned by Azly Othman to do the weight calculation for the A-Frame pontoon. The calculation need to be done by each part. Then, he reviewed my calculation and used it as his reference for him because of some changes on the design.

6/02/2010

8th week of internship

This week, I had attend the meeting regarding the Sapangar project. In this meeting, certain issue had been reviewed for the improvement. The issues reviewed are regarding the vessel to be used for the project, MOB plan suitable date and the selection of the barge with the required specifications to rent for the project.

In the same week, I had been assign to design an A-Frame pontoon for the project to be used.
A-Frame pontoon function to deploy an anchor to the required area.

I used the engineering software (autocad 2007) to design the pontoon.

Here is the drawing that been done after had some discussion with Ahmad Shahir (field engineer) based on his experience on the previous project;











This is the reference for the drawing. A-Frame pontoon that had been used in the previous project.